In Ivano-Frankivsk, a rehabilitation center is being built with dubious estimates and contractors

By the end of 2026, Ivano-Frankivsk should have a rehabilitation center worth 1.2 billion hryvnias, but already at the stage of the project was overpayment for more than UAH 23 million. Construction is carried out by a firm that appears in criminal proceedings, and the documentation was prepared by the spouse related to the person involved in the case of the State Council.

The project is responsible for the Department of Community Development and Territories of the Ivano-Frankivsk Regional State Administration. The tender won LLC "Prombudservice-Kosiv"-the only participant of the auction. The company announced in a row for UAH 1.18 billion, of which UAH 556 million is provided for the purchase of equipment and furniture.

Our money journalists found that the estimates were significantly inflated. For example:

  • Window blocks cost 34.5 thousand UAH/m² - twice as expensive than in Okhmatdita (17.7 thousand UAH/m²).

  • Fire doors were ordered for 22.2 thousand UAH/m² - at a market value of 6.6-7.4 thousand.

  • Reinforcing steel will cost 55.2 thousand UAH/t, while on the market - about 34.1 thousand.

  • Concrete and gas blocks are also purchased with significant overpayment - 6.3 thousand UAH/m³ and 6 thousand UAH/m³, respectively, which is much higher than the average market prices.

The project was executed by Arkon from Brovary, owned by Kateryna Kizimenko, and the examination - the Institute of Research Institute under the guidance of Matthew Kizimenko, her husband. He is the son of Oleg Kizimenko, a former pro -Russian official from Sevastopol convicted in Ukraine for separatism.

The contractor-Prombudservice-Pastes-was founded in 2021. In October 2023, the company received another large in a row-UAH 471 million for hospital reconstruction in Verkhovyna. It also appears in a criminal case on a possible theft of funds of the regional budget when repairing objects for displaced persons. Police found facts of failure to perform the work in full and possible conspiracy of employees with the contractor.

The rehabilitation center is erected on the basis of an unfinished maternity hospital on the street. Fedkovich, 91, at the regional hospital. The project involves the creation of a medical facility for 80 beds with shelter, rehabilitation halls and a family -type hotel for patients and relatives.

Despite the ambitious plans, the history of the tender raises many questions - both about the integrity of the performers and the effective use of budgetary funds.

spot_imgspot_imgspot_imgspot_img

popular

Share this post:

More like this
HERE

Restoration in Cherkasy style: Regional State Administration signed a deal for UAH 47.9 million for a house in Uman with prices doubled

The Construction Department of the Cherkasy Regional State Administration, headed by Igor Taburets...

Singer Dasha Astafieva touched the network with family photos

40-year-old singer and model Dasha Astafieva shared heartfelt home...

BaDM company blocks AMCU fine and blackmails the state by stopping the import of medicines

The Ukrainian pharmaceutical market continues to recover after the largest...

NACP found over UAH 3.3 million in unsubstantiated assets from a judge of the Kyiv-Svyatoshynskyi court

The National Agency for the Prevention of Corruption has identified signs of an unfounded...

Doctors have named popular fruits that can worsen liver function if overeaten

Although most fruits are considered a healthy part of the diet,...

Schemes at Energoatom: corruption in the reconstruction of the nuclear power plant and laundering of millions through Wallet One

Senior officials of JSC NNEGC Energoatom, including the former minister...

Yermak is preparing a major interview with Western media to influence peace talks

Andriy Yermak is preparing to give a big interview to one of the leading...

Online marriage breaks records: over 18 thousand digital marriages registered in Kyiv

In 11 months of 2025, 24,261 couples registered...