The Carpathian police ordered the construction of UAH 236 million with overpayment of more than 7 million investigations

On June 23, the General Directorate of the National Police in Ivano-Frankivsk Oblast concluded an agreement with the Grand-Grandeverbud LLC for the construction of engineering networks and infrastructure facilities of the police training complex in the amount of UAH 236.23 million. This is evidenced by information in the system "Prozorro".

The works include earthworks, sewage laying, water supply, electricity arrangement, coverage and landscaping. The project was developed by UKRThe Engineering LLC. The contract price is solid and does not take into account risks or inflation.

At the same time, the analysis of prices for materials showed that at a number of positions tender prices are significantly higher than market:

  • Georete H200 costs 358 UAH/sq.m, in Ivano-Frankivsk stores-290 UAH/sq.m (difference 19-23%);

  • A400C armature 14 mm was estimated at 43 860 UAH/t, while local sellers-32 500-34 160 UAH/t (20-25% cheaper);

  • Concrete trays B1-22-75 cost 2 304 UAH/pc in the contract, and competitors-1 096-1 655 UAH/pcs (30-50% cheaper);

  • MEGA DN300 H310 tray with a cast iron grille - 22 772 UAH/poll in the tender, and on the market - about 19 000 UAH/poll (15% cheaper);

  • Concrete B10 M150 was estimated at 3 816 UAH/cubic meter, suppliers-2 810–3 475 UAH/cubic meter (9-25% cheaper).

According to experts, overpayments can exceed UAH 7 million in these positions alone.

Competitor LLC "Grandwerbud"-Auster-Don LLC-offered the price of 735 thousand UAH lower, but was rejected due to formal inconsistencies in the tender documentation.

To participate in the tender, it was required to confirm the availability of a minimum of 16 pieces of equipment, the availability of qualified engineers with appropriate experience, permits and previously permits at least 35% of the expected cost.

LLC "Building Firm Grandraverbud" was founded in 2019, the owner - Mikhail Gavrilyak, the head - Timur Abduuramanov. The company is already in criminal proceedings about the possible overestimation of the volume of materials on a contract for the military unit worth UAH 44.97 million. According to the investigation, the company could overestimate the cost of reinforcement by over UAH 2.86 million.

From the foundation, the company received state contracts totaling more than UAH 520 million.

spot_imgspot_imgspot_imgspot_img

popular

Share this post:

More like this
HERE

Tax changes for online income, how the new automatic data exchange system will work

From 2025, Ukrainians earning through digital platforms...

Financial assistance for utilities, new opportunities for families with disabilities

Some Ukrainians may receive additional financial support to pay...

Ukrainian employers are increasingly attracting migrant workers

In Ukraine, employers have begun to actively recruit migrant workers for...

What products help reduce radiation exposure?

In a full-scale war, you need to be prepared for anything....

Major breakthrough in breast cancer treatment, new drug reduces risk of recurrence by 42%

An international group of scientists has announced a breakthrough in cancer treatment...

Pharmacy chains against the manufacturer, what is happening with the company "Darnitsa"

Between one of the largest domestic drug manufacturers and leading...

Will women be mobilized in 2025, clarification on rules and responsibilities

Despite the fact that a full-scale war is ongoing in Ukraine, mobilization...

A bank employee in Odessa transferred a client's savings to her own card

In Odessa, a bank employee embezzled almost 400...