In Ivano-Frankivsk, a rehabilitation center is being built with dubious estimates and contractors

By the end of 2026, Ivano-Frankivsk should have a rehabilitation center worth 1.2 billion hryvnias, but already at the stage of the project was overpayment for more than UAH 23 million. Construction is carried out by a firm that appears in criminal proceedings, and the documentation was prepared by the spouse related to the person involved in the case of the State Council.

The project is responsible for the Department of Community Development and Territories of the Ivano-Frankivsk Regional State Administration. The tender won LLC "Prombudservice-Kosiv"-the only participant of the auction. The company announced in a row for UAH 1.18 billion, of which UAH 556 million is provided for the purchase of equipment and furniture.

Our money journalists found that the estimates were significantly inflated. For example:

  • Window blocks cost 34.5 thousand UAH/m² - twice as expensive than in Okhmatdita (17.7 thousand UAH/m²).

  • Fire doors were ordered for 22.2 thousand UAH/m² - at a market value of 6.6-7.4 thousand.

  • Reinforcing steel will cost 55.2 thousand UAH/t, while on the market - about 34.1 thousand.

  • Concrete and gas blocks are also purchased with significant overpayment - 6.3 thousand UAH/m³ and 6 thousand UAH/m³, respectively, which is much higher than the average market prices.

The project was executed by Arkon from Brovary, owned by Kateryna Kizimenko, and the examination - the Institute of Research Institute under the guidance of Matthew Kizimenko, her husband. He is the son of Oleg Kizimenko, a former pro -Russian official from Sevastopol convicted in Ukraine for separatism.

The contractor-Prombudservice-Pastes-was founded in 2021. In October 2023, the company received another large in a row-UAH 471 million for hospital reconstruction in Verkhovyna. It also appears in a criminal case on a possible theft of funds of the regional budget when repairing objects for displaced persons. Police found facts of failure to perform the work in full and possible conspiracy of employees with the contractor.

The rehabilitation center is erected on the basis of an unfinished maternity hospital on the street. Fedkovich, 91, at the regional hospital. The project involves the creation of a medical facility for 80 beds with shelter, rehabilitation halls and a family -type hotel for patients and relatives.

Despite the ambitious plans, the history of the tender raises many questions - both about the integrity of the performers and the effective use of budgetary funds.

spot_imgspot_imgspot_imgspot_img

popular

Share this post:

More like this
HERE

Bacteria and insomnia: why the state of the gut and mouth affects rest

When we fall asleep, the body's work doesn't stop. Together...

From investments to lawsuits: what is behind the debts of Chernihiv CHP

During the war, when every budget hryvnia counts...

The government is launching a mass certification of customs officers: about 10 thousand employees will be tested

The Cabinet of Ministers approved a new procedure for certifying customs officials...

Former heads of the Kyivmisksvitla department declared suspicious due to overpayment of UAH 14.5 million for streetlights

In Kyiv, the former head of the department of the Kyivmisksvitlo municipal enterprise was informed about...

Magnesium deficiency: how it manifests itself and who it most often affects

Magnesium deficiency is a common but often unnoticed condition that...

Stolichny Market: How State-Owned Plots Ended Up in Private Hands

Anti-corruption authorities are investigating the land deal surrounding the wholesale market...

SAPO demands confiscation of property of MIA official Popovych worth over UAH 8 million

The Specialized Anti -Corruption Prosecutor's Office filed a lawsuit against the Supreme Anti -Corruption Court ...