Promteks PE received UAH 171.45 million from the Kharkiv City Council to repair a damaged building at inflated prices

According to project , the Department of Improvement, Reconstruction and Reconstruction of the Kharkiv City Council signed a contract with the "Promtex Construction Company" PE on October 9 for the overhaul of an apartment building damaged by shelling. The contract amount is UAH 171.45 million, financed by the Ukraine Facility. The work should be completed by the end of 2026.

The project was developed by the private enterprise "Pallada", the expertise was carried out by the Kharkiv branch of the state enterprise "Ukrderzhbudekspertyza". The estimate includes delivery of materials around the city, but experts draw attention to the obvious overestimation of certain items. Thus, the documentation indicates prices that significantly exceed market offers:

  • NT Facade 135 slabs (150 mm) — 1,193 UAH/sq. m (market: 534–765 UAH/sq. m);

  • polystyrene EPS 200 Graphite 150 mm — 1,405 UAH/sq. m (market price: 634–765 UAH/sq. m);

  • cable VVG ngd 5x10 — 392 UAH/m (market price: 299 UAH/m);

  • Weber Therm S80 reinforcing adhesive — 23 UAH/kg (market price: 6 UAH/kg).

According to experts, the probable overpayment for the listed positions alone could amount to at least UAH 5 million. There was a cheaper competitor at the auction, Avtomagistral-Zahid LLC, which offered UAH 17.65 million less, but its offer was rejected due to alleged technical inconsistencies.

PE "Construction Firm "Promtex"" is part of the "Building Group" consortium, whose owners are Ruslan Maly, Stanislav Brovin and Natalia Golovko. The consortium is associated with the investment and construction corporation "Avantage", a key person in which is the former deputy of the Kharkiv City Council and People's Deputy Anatoliy Denysenko. Since 2016, Promtex has received government orders for a total of UAH 3.74 billion, mainly from the current customer.

An explanatory note with a detailed justification of the cost of works and materials has not been made public, which leaves open the issue of transparency of the estimate assessment and the appropriateness of the contractor's selection. The customer and the contractor must provide full explanations regarding the formation of prices in the estimate and the reasons for rejecting the cheaper offer in order to eliminate suspicions of unjustified expenditure of budget and donor funds.

spot_imgspot_imgspot_imgspot_img

popular

Share this post:

More like this
HERE

Simple recipes for weight loss: how to eat deliciously and lose weight without stress

Losing weight doesn't necessarily mean starving yourself or completely giving up...

Former Deputy Head of Kharkiv OVA Oleksandr Skakun Created Billion-Dollar Shadow Fuel Scheme

One of the most powerful shadow fuel schemes is being formed in the Kharkiv region...

On the front, the Russian Federation is changing tactics: small groups, combat reconnaissance and drones

Russian troops continue to try to advance on the front, using small...

Singer Ani Lorak showed her daughter and mother: photos of the traitor's family caused a flurry of comments

47-year-old Ani Lorak, who after a full-scale invasion finally chose...

How 132 million was withdrawn from “Centrenergo”: a scheme with fictitious coal

Corruption scandals in Ukraine's energy sector are becoming increasingly large-scale...

Up to 1.1 million hectares under water: experts named the scale of flooding of the Ukrainian coast in the event of warming

Global warming could significantly change the map of Ukraine by...